Draft JSERC (Framework for sharing of charges for Intra-State Transmission System) Regulations, 2019

Mar 29, 2019 | by Avantis RegTech Legal Research Team


The Jharkhand State Electricity Regulatory Commission (JSERC) on March 29, 2019, has issued Draft called JSERC (Framework for sharing of charges for Intra-State Transmission System) Regulations, 2019.

These Regulations will be applicable for the existing transmission system and projects.

Scope of the Regulations:

Ø  Annual Transmission Charges shall be shared amongst the following categories of beneficiaries who are currently using the Intra-State Transmission System (InSTS) or the InSTS to be developed through Section 62 and Section 63 of the Electricity Act, 2003:

a)      Generating Station (s) in the State;

b)      Distribution Licensee (s) in the State;

c)       Transmission Licensee (s) in the State;

d)      Any other customer including Captive Generating Stations and Open Access  customers; and 

e)      Any designated entity representing a physically connected entity as per clauses (a), (b) and (c) above

Ø  For the existing InSTS in the State, the framework for sharing of charges was given in JSERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2015. With the notification of these Regulations, the framework given in this regulation shall be applicable for all existing and new InSTS.

Click here to download the Draft Regulations.